List of the most significant references
in the field of project and production documentation and engineering:
|
Date of completion |
Subject-matter |
Customer |
|
Under implementation |
Detail engineering of recovery boiler for combustion of sodium hydroxide and natural gas for Lenzing, Austria, 31 t/h, 7.9 MPa, 480°C |
RAFAKO, S.A. |
|
Under implementation |
Detail engineering of recovery boiler for combustion of black liquor from cellulose production process, of fumes from production of cellulose and natural gas for Lenzing, Austria, 145 t/h, 8.4 MPa, 485°C |
RAFAKO, S.A. |
|
January 2011 |
Procuration, coordination and control of construction of power plant of the peak source 58 MWe PPC Bratislava |
PPC Energy, a.s. |
|
March 2010 |
Detail engineering of boiler for municipal waste combustion for “Waste to Energy Plant”, Bern, Switzerland, 70 t/h, 4 MPa, 400°C |
MARTIN, GmbH |
|
November 2009 |
Documentation for territorial decision for the peak source of 58 MWe Prostějov |
Moravia Energo, a.s. |
|
January 2009 |
Documentation for territorial decision, building permit and implementation of the peak source 58 MWe PPC Bratislava |
PPC Energy, a.s. |
|
April 2008 |
Feasibility study of construction of the peak source 58 MWe Brno. |
JET Power, a.s. |
| January 2008 | Detail engineering of recovery boiler for combustion of sodium hydroxide and natural gas for Lenzing, Austria, 31 t/h, 7.9 MPa, 480°C | SES Tlmače, a.s. |
| July 2007 | Feasibility study of construction of the peak source 58 MWe PPC Bratislava | PPC Energy, a.s. |
| September 2006 | Documentation for building permit of cogeneration unit for biomass combustion 2.5 MWe | Obec Ľubica |
| November 2005 | Feasibility study of construction of steam-gas cycle at compressor stations in Veľké Kapušany | SPP, a.s. Bratislava |
| July 2005 | Detail engineering of reconstruction of combustion chamber and EKO boiler for biomass combustion with the capacity ot 24 t/h, 4 MPa, 425 °C in Wilburgstetten, Germany | Rettenmeier Holding AG, Nemecko |
| December 2004 | Interconnecting piping of new recovery boiler and cellulose factory. | NEUSIEDLER SCP, a.s. Ružomberok |
|
January 2003 |
Study for reconstruction of boiler K4 with the capacity of 120 t/s with a possibility to increase the output to 150 t/h |
Kappa Štúrovo, a.s |